Project Description

Triton Engineers designed a new mooring system for BAE System’s 4000 ton drydock which consisted of a series of five reinforced concrete dolphins equipped with special grippers for securing the drydock. The analyses performed by Triton addressed the forces imposed on the mooring system by storm wind and oceanographic environmental loads in addition to the […]

Project Details

Article Date 08/31/1999 Categories Waterfront
Completed March 2014Client BAE Systems